Dundee Board of Education Recap

In preparation for the 2019 school year, the LaScala IT representatives presented results of their initial findings and some suggestions for the DCS technology plans. They will be presenting financial information for these suggestions at the August Board meeting. This will be extremely helpful for the 1:1 Learning Initiative for the 6-8th grade staff and students which is scheduled to begin in January 2019.
The following13 policies we reviewed at the Board meeting and the Board will take action on these policies at the August meeting.
0143.1 – Revised; Public Expression of Board Members
1421 – Revised; Criminal History Record Check – Administration
3121 – Revised; Criminal History Record Check – Professional Staff 
4121 – Revised; Criminal History Record Check – Support Staff
4162 – Revised; Controlled Substance and Alcohol Policy for Commercial Motor Vehicle (CMV) Drivers and other employees who perform safety sensitive functions
5111 – Revised; Eligibility of resident/non-resident students
7540.02 – Revised Web Accessibility, Content, Apps, and Services
8321 – Revised; Criminal Justice Information Security (Non-Criminal Justice Agency)
7530 – Revised Policy – Phase IV Technology Update – Lending of Board Owned Equipment 
7542 – Revised Policy – Phase IV Technology Update – Access to District Technology Resources and/or Information Resources from Personal Communication Devices
7543 – Revised Policy – Phase IV Technology Update – Utilization of the District’s Website and Remote Access to the District’s Network
3120A – Revised Policy – Hiring Practices

Ms. Gina Mann has been employed as our next Speech and Language Therapist through The Stepping Stones Group (Cumberland Therapies.
Ms.Becky Noworyta has been hired as the Elementary Full Year Secretary position. 
The Middle School Cafeteria will be the site of the Meet Up to Eat Up Summer Feeding Program beginning Monday, July 30 and running until Thursday, August 23. 
If you are interested in becoming a Board of Education member, please contact Ms. Wilson at 734-529-2350 ext. 11000 for details.  The deadline to register for the November election is Tuesday, July 24 at 4pm.
Forthcoming summer meetings of the Board and DCS are as follows: Village of Dundee/Dundee Community Schools joint Public Meeting – Tuesday, August 7th at 7:00pm at the Dundee Village Office; Regular DCS Board of Education Meeting – Monday, August 13th at 5:30pm in the Middle School Media Center
Superintendent Manuszak reports that Phase 1 Bid Pack 1 & 2 work on the Bond includes:
1) HS Natatorium – The “dance floor” is fully assembled thus created a floor for the ceiling so this can be painted and treated now.  The rafters and the ceiling will become a light gray and we have been told by our contractor that this will be good for 15 years.  The scoreboard and new starting blocks have been ordered and once the painting is complete these can then be installed. Expected completion by the first part of August.
2) HS Roof – The light brown metal roof is now being installed.  Full installation is under way.  The expected completion date is the first part of October for this project.
3) ES Lockers – The old lockers have been removed and the new ones will be installed shortly.  This project will be completed before school begins.
4) HS Football Field Stadium Seating – The concrete has been poured for both the home and away sidelines.  We are anticipating the stadium seating to be installed sometime this week.  This project will be completed before Aug. 23 which is our first home football game.
5) HS/MS parking lots – The old parking lot material has been removed and we are now waiting for the base dirt to be delivered and can then make sure to add the new asphalt over this when ready.  All new downspouts will be connected to the storm sewer.  This project will be completed before our first home football game on August 23.
6) MS Safe Entry – Work has begun on creating a new entryway into our MS.  This project will be completed before the school year begins.
7) ES Fire Alarm System – This work has begun and it will be completed before the school year begins.
8) HS Gymnasium Floor – Work has begun on this project where the old damaged wood has been torn out and the new wood will be installed. Once this is installed the new wood along with the old floor will be completely sanded and refinished.  We expect this project to be completed before the school year begins.
9) HS/MS Gym Walls – The MS Gym Wall has been removed and the new MS Gym Curtain will be installed soon.  The HS Gym Wall has yet to be removed, but we are planning to have this done before the beginning of the school year.
10) The HS Main Entry – The work has not yet started on this improvement, but will begin shortly.  We expect this to be completed before the beginning of the school year.
11) HS Stage Lighting and ES Sign – This work has not yet begun, but we expect this work to be completed sometime before the end of September.
12) MS Natatorium/Gymnasium/Cafeteria Boilers – This work has begun and is expected to be completed before the beginning of the school year.
13) Transportation parking lot – Not begun yet, but this will also begin soon and we expect this to be completed before the start of the school year.
Dundee GSRP Pre-School – We just learned that our GSRP Pre-School has once again secured and earned the highest rating of a five-star program! 